Oakland Avenue gets its ribbon cutting on Saturday, December 5, at Wood Square, in the middle of Shorewood's Winterfest.
The Shorewood Business Improvement District is partnering with the Village of Shorewood to hold the ceremony during this year's tree lighting. The BID's event page calls it a celebration of "the opening of Oakland Avenue after a year long reconstruction project." The Village's projected schedule set final completion for December 1, four days before the ceremony, and noted that the dates could change. That puts the projected finish and the celebration in the same week, and those days decide what the street feels like heading into winter.
The reconstruction covers Oakland Avenue from Capitol Drive north to Glendale Avenue, crossing Elmdale Court, Kenmore Place, Jarvis, Wood, Olive and Marion Streets, and Lake Bluff Boulevard. According to the Village's April 2024 project presentation, the work was first planned for 2022. It was deferred after the pandemic, rescheduled to 2025, and pushed back again when WisDOT scheduled its own State Highway 32/Lake Drive project for 2025.
Crews finally started in February 2026. The project website lists completion in December 2026. Holding the ribbon cutting at Winterfest puts the ceremonial reopening on a night the BID already runs every year, with Santa, a vintage sleigh, and specials at shops along the corridor.
Winterfest is free and runs from 3:30 to 6:30 p.m. Santa travels between stops in the BID's vintage sleigh, and every stop has something of its own going on. Here is the order, using the times from the BID's Winterfest page:
There's one more stop for families with letter writers. A letters-to-Santa mailbox sits outside Foxhole Craft Beer Shop & Kitchen, courtesy of a local Allstate agency.
The Wood Square stop is the one to plan around. The BID's itinerary puts the lighting and ribbon cutting at 5:45. Another line on the same page places the ribbon cutting "during the tree lighting at 6pm." If you arrive by 5:45, you'll catch it either way. You'll also be close to the cookie table before the crowd forms around the tree.
Shorewood has been driving around this project for most of the year, but much of the work happened where no one could see it. The Village's presentation lists the scope:
For anyone walking to the tree lighting, the bump-outs are the change you'll feel. The presentation scheduled them in two passes: the west side was built together with the southbound lanes, and the east side came last, along with pavement marking. Wider corners mean shorter crossings at the cross streets. That matters on a December evening when a sleigh, strollers and a crowd are all moving between Blackbear, SCOUT, Draft & Vessel and Wood Square in the same three hours.
The water work explains why the year went the way it did. The presentation's phasing began with four to six months of water main work, moving about one to two weeks per block, with rolling parking closures. Each side of the road was rebuilt after that, with no parking on Oakland during the road phases. Its projected timeline had utility installation running from February or March into June or July, then road reconstruction from June through November.
The ribbon cutting and the final punch list are on almost the same calendar. Here are the dates the Village and the BID have published:
| Date | What's scheduled |
|---|---|
| November 6 | Latest project update: parking lanes on both sides of Oakland stay closed for landscape restoration, paver block installation, pavement marking, and street and signal lighting work |
| Early December | Oakland's northbound and southbound parking lanes scheduled to stay closed until then |
| December 1 | "Final completion" date in the Village's 2024 projected schedule |
| December 5 | Winterfest, with the ribbon cutting at Wood Square |
| December 2026 | Completion month listed on the project website |
So the pavers, lighting, new landscaping and pavement markings make up the last stretch of work before the ribbon goes up. The presentation itself calls its schedule "subject to change," with the actual timing set by the contractor. The project website posts a weekly forecast, so check it in the days before December 5 to see whether the parking lanes are back.
Until they are, the BID's parking map is still the guide. The project site links a downloadable version and asks residents and visitors to keep supporting the businesses along Oakland while the work wraps up. For a walking event built around five stops, it makes sense to park once and go the rest of the way on foot.
The presentation says the Village's Ordinance 3043 requires replacement of all public and private lead service lines. Properties in Village lead service line project areas were eligible for Shorewood Water Utility assistance covering up to 50% of the cost of replacing the private portion. As the presentation describes it, the owner's remaining share could be repaid through a 0% loan in 12 equal installments on the next 12 utility bills, about three years, with no prepayment penalty. Past-due installments go on the tax roll.
If your home connects to the water main under Oakland, that loan may still be showing up on your utility bill as the street reopens. The figures above come from the Village's April 2024 presentation, which also points to the Village's lead services page for more information. This is general information, not legal, tax or financial advice, so please confirm the terms for your own property with the Village and the right professional.
If you're bringing young kids, start at Blackbear at 3:00 for the craft table. You'll have time to meet Santa at 3:30 and follow the sleigh north through the afternoon. If the grown-ups want a stop of their own, SCOUT's bubbles at 4:15 and Draft & Vessel's mulled wine at 5:00 come right before the Wood Square lighting. Either way, Wood Square around 5:45 is where the tree, the Menorah and the ribbon all come together. Camp Bar Shorewood at 6:15 closes out the night.
Once the ribbon is cut, Oakland Avenue becomes a selling point for every home within walking distance of it. If you're wondering how the rebuilt street and the year of construction show up in your home's value, Elissa Berkoff would be glad to talk it through with you. Let's connect, and get your instant home valuation.
Elissa is committed to providing exceptional value, personal care and service tailored to the requirements of her clients. The real estate experience that Elissa offers goes over and above what her clients expect. This is important as her goal is not to simply meet their expectations but to exceed them, even well beyond closing.